CatholicBoardHuron-Superior Catholic board trustees were updated on Wednesday on the most recent construction of the new St. Marys College.  Most of that construction is either ahead of or on schedule, with the only work remaining is to painting in the north section of the school and plumbing in the facility’s south section.  The rest of the building is primarily 85 to 100 percent completed six months before the new SMC open its doors.